  1. ForewordIntroducing the EXA Manufacturing Operations Series
  2. Part 1MFG EP01. The Idle Five-Axis Machine and the Mirage in the Conference Room
  3. Part 1 · Commentary 1MFG EP01 Commentary 1. Departmental Performance and Factory Performance
  4. Part 1 · Commentary 2MFG EP01 Commentary 2. How Work in Process and Waiting Build Up
  5. Part 1 · Commentary 3MFG EP01 Commentary 3. Synchronizing Production Planning and Execution
  6. Part 1 · Commentary 4MFG EP01 Commentary 4. Shop Floor Records and Updating Estimates
  7. Part 6MFG EP02. How Do We Calculate the Delivery Date We Promise a Customer? — Part 1
  8. Part 7MFG EP02. How Do We Calculate the Delivery Date We Promise a Customer? — Part 2
Part 1 · Commentary 4

MFG EP01 Commentary 4. Shop Floor Records and Updating Estimates

How shop floor records validate planning parameters and update the basis for production schedules

Article overview

The operating question behind this article

Which records should validate production scheduling parameters, and how should those parameters be updated?

What the article argues

Measure actual processing times at the bottleneck by operating condition and estimate both the mean and its uncertainty. Present the results as proposed changes and apply them to scheduling parameters after the responsible person reviews them.

This is the fourth commentary on the opening episode of the EXA Manufacturing Operations Series, “The Idle Five-Axis Machine and the Mirage in the Conference Room.” The first three commentaries examined how departmental decisions affect plant-wide performance, how those decisions create work in process and waiting, and how to coordinate preparation and inspection around the bottleneck schedule.

Commentary 3 ended with a question. How much confidence can a production schedule place in parameters such as standard times, tool life, and inspection times?

In the fictional plant, planning parameters repeatedly diverged from actual conditions. The standard time in the master data was shorter than the actual cutting time, tools wore out sooner than expected, and final measurement ran past its reserved slot.

The relationship between planning values and actual results changes with the material lot, operating conditions, and geometry of the part being measured. Planning parameters also carry the uncertainty of the shop floor, which can pull execution away from the plan.

This commentary examines six questions.

  1. How do master data values differ from shop floor records, and how should those records be classified (Section 1)?
  2. What happens to a detailed schedule based on every operation's planning parameters when those parameters miss actual conditions (Section 2)?
  3. Which parameters does a bottleneck-centered schedule treat precisely, and where does it absorb the remaining errors (Section 3)?
  4. Under what conditions should bottleneck machining times be measured for scheduling (Section 4)?
  5. How do measurements update estimates of planning parameters, and when do those updates enter the schedule (Section 5)?
  6. As records accumulate, what evidence supports capacity decisions such as adding equipment (Section 6)?

The figures and operating conditions in the worked examples are assumptions chosen to illustrate the principles. They are separate from the fictional plant's measurements. Figures taken from the story are identified by chapter.


1. Master Data Values and Shop Floor Records

In Chapter 4, the sales director presented a utilization figure of 94.8% for the three five-axis machines. The calculation used the start and completion barcodes scanned by the operators. Martin downloaded the machine controller logs for the same period and aligned them with job sheets and measurement intake and approval times. Actual metal cutting occupied less than half the day.

The shop supervisor and inspection staff classified the remaining intervals as setup, waiting for first-piece measurement, or waiting for material from the preceding operation. They separately identified tool test runs and intervals in which the program ran without material. The barcode records counted all of these intervals as operating time.

The reconciliation revealed another kind of discrepancy. When Martin isolated the time during which the spindle actually ran and compared it with the master data, he found that cutting time per unit for Meriden's housings and manifolds exceeded the standard. The housing geometry had changed, making the former cutting conditions unsuitable. This difference arose in machining itself. Some records also failed to match. Martin flagged unverified intervals and left their causes unassigned.

The reconciliation divides the records into four categories.

CategoryEvidence from the storySignificance for scheduling
MachiningIntervals in which the spindle rotated and cut metal (Chapter 4)Compare with the standard time in the master data
Setup and tool changesTime spent finding tools and changing fixtures (Chapter 4), and replacement due to tool wear (Chapter 9)Measure and manage separately from machining time per unit
WaitingWaiting for first-piece measurement or for material from an upstream operation (Chapter 4)Idle time arising from preparation or coordination between operations
Record errors or unverified intervalsConflicting records (Chapter 4)Exclude from estimation until the cause is verified

The discrepancies extended beyond machining time. In Chapter 9, the end mill used to rough out the housing bore was scheduled for replacement every 30 parts, but the wear-limit alarm sounded on the 22nd part. The supervisor suspected that the latest titanium lot had higher tensile strength than the previous one. He reduced the cutting speed for bore roughing alone and decided to replace the tool every 20 parts, before the alarm sounded.

In Chapter 8, the team requested one hour for final inspection. In Chapter 11, final measurement of the housing started at 9 a.m. and finished at 11 a.m.

Each discrepancy had a different character. The standard cutting time failed to reflect the conditions required by the revised geometry. The supervisor attributed premature tool wear to the material lot. Final measurement took one hour longer than its reservation. The fact that planning values differ from actual results does not by itself establish what to change. Classifying the records reveals both the causes and the values that need updating.

Barcode operating records classified as machining, setup and tool changes, waiting, and errors or unverified intervals

2. Schedules That Depend on Every Parameter and the Spread of Disruption (Delays)

Consider a schedule that assigns a start and finish time to every job at every operation. Given the parameters for each job and the availability of equipment and labor, it can calculate a sequence that fits the chosen objective and resource conditions. The schedule is precise when all its parameters match actual conditions. When one of them is off, the effects can extend beyond that job.

The following worked example uses a production line with two operations, grinding followed by milling. The planned machining time is eight hours per job at each operation. The plan runs five jobs in sequence without interruption: grinding from hour 0 to hour 40, and milling from hour 8 to hour 48. Times are elapsed hours from the start of the plan.

Actual machining times vary around the planning values. Grinding can take between 5 and 11 hours per job, and milling between 7 and 10 hours. For these five jobs, assume grinding takes 10, 10, 6, 6, and 8 hours respectively, while milling takes eight hours each time as planned. Grinding takes 40 hours in total, exactly as planned. Its average machining time equals the planning value of eight hours.

The cumulative deviation in the table is how many hours late a job finished, calculated as actual completion time minus planned completion time. Zero means the job finished as planned.

JobGrinding plan (h)Grinding actual (h)Grinding cumulative deviation (h)Milling plan (h)Milling actual (h)Milling cumulative deviation (h)
10~80~1028~1610~182
28~1610~20416~2420~284
316~2420~26224~3228~364
424~3226~32032~4036~444
532~4032~40040~4844~524

Grinding Job 1 took ten hours and finished at hour 10 instead of hour 8. Milling was supposed to start Job 1 at hour 8 but had no work to receive, so it sat idle for two hours. Grinding Job 2 also took ten hours and finished at hour 20 instead of hour 16. Milling finished Job 1 at hour 18, but Job 2 had yet to arrive, so it sat idle again until hour 20. These two interruptions brought milling's cumulative deviation to four hours.

Grinding Jobs 3 and 4 each took two hours less than planned, bringing grinding's cumulative deviation back to zero. Milling, however, was still processing the earlier jobs it had received late. Grinding finished Job 3 at hour 26, but milling was occupied with Job 2 until hour 28. Grinding finished Job 4 at hour 32, but milling could not start that job until hour 36. The time saved in grinding did not bring milling forward.

Job 5 took eight hours at both operations as planned, but milling began at hour 44, four hours late because of the previous job, and finished at hour 52.

Grinding finished all five jobs at hour 40 as planned. Milling finished at hour 52, four hours late. Grinding averaged exactly the planned machining time, yet the line delivered its output four hours late.

When operations depend on one another, an upstream delay stops the downstream operation if it runs out of ready work. When the next upstream job finishes early, the downstream operation cannot start it if it is still working on an earlier job. Increases and decreases in machining time therefore do not cancel out downstream.

In a schedule with no spare time at any operation, downstream time lost for lack of ready work cannot be recovered by later jobs or by recalculating the schedule. If milling times vary too, the same pattern repeats from operation to operation.

Disruption spreads throughout the plant, and the time lost is gone for good.

Planned and actual grinding and milling schedules, with cumulative deviations by job

Reservations for shared resources can magnify delays. In the next example, orders X and Y each pass through operations A, B, and C in sequence. Operation A is initial machining, B is machining on the bottleneck equipment, and C is inspection in the metrology room. Each operation handles one order at a time.

The metrology room is already booked for order Z from hour 7 to hour 10. The plan leaves no slack between jobs. Each inspection must run without interruption. Times are measured from the start of the plan. In the table, 2.5, 6.5, and 10.5 mean 2 hours 30 minutes, 6 hours 30 minutes, and 10 hours 30 minutes after the start.

JobOperationPlanned slot (h)After X's 30-minute overrun at A (h)Change
Machine XA0~20~2.530 minutes late
Machine X at bottleneckB (bottleneck)2~62.5~6.530 minutes late
Inspect XC (metrology room)6~710~114 hours late after moving behind Z
Inspect ZC (metrology room)7~107~10Unchanged, reservation kept
Machine YA4~64~6Unchanged
Machine Y at bottleneckB (bottleneck)6~106.5~10.530 minutes late because X finished late
Inspect YC (metrology room)10~1111~121 hour late after moving behind X

X was scheduled to spend two hours at A, but it took two and a half hours and finished at hour 2.5. Its machining at B began correspondingly late and finished at hour 6.5, 30 minutes behind plan.

X had a reservation in the metrology room from hour 6 to hour 7. It arrived at hour 6.5, leaving only 30 minutes for an inspection that needed a full hour. The room was booked for Z from hour 7 to hour 10. To honor Z's booking, the room moved X behind Z and inspected it from hour 10 to hour 11. X finished four hours later than the planned hour 7. Inspecting X ahead of Z would have delayed Z's reservation instead.

Y was affected too. Its machining at B could start only when X finished at hour 6.5 and ended at hour 10.5. Its inspection was supposed to start at hour 10, but the room was inspecting X from hour 10 to hour 11, so Y's inspection started at hour 11. Y finished one hour behind plan.

A 30-minute delay reached another order through operation dependencies and a shared resource reservation, and became a four-hour delay for X. X's completion depended on the next available slot in the metrology room.

A 30-minute overrun for order X at operation A changes the inspection schedule for X and Y while preserving Z's reservation

Both examples show how an error in a planning parameter can affect more than a single job. Grinding finished its last job on time in the first example, but milling finished four hours late. In the second, a 30-minute delay at operation A collided with a metrology room booking and delayed order X by four hours. When operations depend on one another and the schedule has no slack, small deviations lead to downstream stoppages and delays for other orders. The time lost cannot be recovered.

How does a method that schedules the whole plant in detail using every operation's parameters handle this pattern? The industry calls these planning systems APS. The following section examines them from this standpoint.

Do the Claims of Advanced Planning & Scheduling Hold Up?

Since the 1990s, Advanced Planning & Scheduling (APS) has been introduced to factories in many countries as a solution to scheduling problems. Many plants adopted these systems expecting to run the entire factory on an optimal schedule, and adoption continues today.

APS calculates job sequences and times from standard times, setup times, routings, resource availability, and other inputs. The scope and method vary by product and configuration. Calculations that treat processing times as fixed assign start and finish times on the assumption that jobs will take exactly as long as specified.

APS optimization searches for the sequence that gives the best values for chosen measures, such as lateness, number of setups, and overall completion time. Yet plant output does not depend equally on every operation. The bottleneck determines output. Saving time at an operation that does not restrict the bottleneck will not increase plant output. A calculation that fails to distinguish between these resources cannot show which operation's time determines output.

Schedule optimization aims to improve results in an uncertain environment. But a calculation that treats processing times as fixed leaves uncertainty outside the calculation. A calculation meant to overcome uncertainty has, in effect, erased it from its inputs. A fixed-time schedule alone cannot show how far actual processing times will vary around those values or how variation will lead to idle time at the bottleneck and waiting downstream.

Processing times always vary in manufacturing. Even when the same operator uses the same equipment to machine the same item, the time taken varies. Material lots, tool wear, operator skill, and equipment condition all contribute to variation.

Operations also depend on one another because they can begin only when earlier operations finish. Both conditions exist in every plant. When upstream delays leave a downstream operation without ready work, it stops. When the downstream operation is still processing the previous job, it cannot begin the next upstream job even if it finishes early. Time saved upstream cannot offset idle time that has already occurred downstream.

Then there is Murphy's Law. Equipment breaks down, defects occur, material fails to arrive, and another urgent job takes precedence in the metrology room. Problems that can occur will occur eventually. Such disruptions are part of everyday manufacturing. In a schedule with no slack, one disruption reaches beyond the affected job. The delay spreads through operation dependencies and shared resource reservations to the rest of the schedule.

As processing times and resource availability vary, actual times diverge from the calculated schedule. A delay that exceeds the protective allowance carries over to subsequent jobs and shared resource reservations. As the examples show, it can grow beyond the original delay.

Some APS systems first sequence the bottleneck and then schedule other operations around it. Even then, once the bottleneck sequence is calculated, material release and allowances must be managed to keep the bottleneck running and make the schedule executable. If the method calculates detailed times for the remaining operations, it still depends on their processing times and routings. This approach continues to rely on parameters from every operation.

APS providers offer the following functions to deal with shop floor variation.

FunctionIntended effectLimits to examine
ReschedulingRecalculate the schedule after events such as breakdowns or material delaysUpdating actual results leaves future processing times uncertain. If every job varies, rescheduling becomes routine. Frequent changes to sequences and preparation priorities can create extra setups and preparation losses.
Job or sequence lockingLimit changes during rescheduling by locking jobs already started or fixing selected sequencesThis stabilizes shop floor instructions. Other means are needed to absorb variation in the processing times of locked jobs.
AllowancesInsert slack between operations to absorb small delaysThe effect depends on the location and size of the allowance and the resource it protects. A downstream operation still busy with an earlier job cannot start the next one early even when it arrives early. Check which stoppages an allowance reduces and by how much.
Scenario and variation analysisCompare schedules under different conditions. Some products estimate the probability of meeting due dates through simulation with variable processing timesThis requires data and assumptions that characterize key processing times, breakdowns, and material delays. Check how representative those data are and what it takes to maintain them.
Bottleneck sequencing first (some products)Sequence the bottleneck first and arrange the remaining operations around itWhere detailed schedules extend to non-bottleneck operations, their master data and progress also affect schedule reliability. Separately examine how material release and allowances are managed to reduce bottleneck downtime.
Master data managementImprove accuracy by comparing standard times with actual resultsEvery scheduling method needs this work. If schedule accuracy depends on the parameters for all operations, the number of values to maintain becomes a burden.

When processing times and resource availability are stable, schedules calculated from planning parameters may be easier to execute as planned. Yet variation, dependent operations, and disruptions exist in every plant. Even with rescheduling or locking functions, upstream delays propagate downstream, and recalculation cannot recover idle time that has already occurred.

The presence of these functions alone does not establish operational performance. The test is how the bottleneck and production flow are sustained when variation and disruptions occur. Beyond the presence of an optimizer, examine which parts of the schedule are kept precise, which are protected with allowances, and where adjustments are made.

Plants evaluating APS should therefore listen carefully to the claims made for it. The plant that adopts a schedule bears the consequences of executing it. Prospective users should test vendors' claims against their own operating conditions and records. They need to establish how often and how much the schedule changes when parameters miss actual conditions, and what those changes do to throughput, work in process, bottleneck idle time, and additional setups.

EXA approaches this problem through the principles that determine plant output. Shop floor records and mathematical reasoning establish where the bottleneck lies, where uncertainty arises, and where it must be absorbed to keep schedule commitments. Those findings form the basis for the schedule. This is where EXA's principle of addressing business problems with scientific methods leads in production scheduling. The bottleneck-centered schedule in the next section is the starting point.

3. Bottleneck-Centered Scheduling and Spare Capacity at Other Operations

Martin scheduled differently in the story. He set the sequence and times for the five-axis machines first, then coordinated upstream material supply and metrology inspections with that schedule. The housing was to finish machining at midnight at the end of Thursday, and shipment was promised by 5 p.m. Friday. The 17 hours between those points covered downstream work and included room to absorb delays.

Applied from this perspective, the finite capacity scheduling discussed in Commentary 3 schedules the bottleneck in detail. Its job sequence and start and finish times stay within the equipment's available capacity. Non-bottleneck parameters do not set exact times for each job. Errors at those operations are absorbed by the buffers ahead of the bottleneck and before shipment, and by the actual spare capacity of the non-bottleneck equipment.

To absorb upstream delays before they reach the bottleneck, release materials early enough to allow for preparation. This preparation allowance is the interval between the scheduled completion of the upstream operation and the scheduled start of machining at the bottleneck.

In the example in Section 4 of Commentary 3, an upstream operation ran three hours late. With a four-hour allowance, the part still arrived one hour before the scheduled start at the bottleneck, so both its start and completion stayed on schedule. With a two-hour allowance, the part arrived one hour after the scheduled start and the bottleneck sat idle for an hour.

When the bottleneck stays on schedule and downstream conditions stay the same, as they do in this example, the later inspection bookings and schedules for other orders remain intact.

In the story, the allowance before shipment absorbs a downstream delay. Final measurement took one hour longer than its one-hour reservation. It finished at 11 a.m., and the report was ready at noon. Shipment was promised by 5 p.m. Friday, and the truck carrying the housing left at 4:40 p.m. The metrology room's planning value was off, but the time before shipment absorbed the difference.

Even at non-bottleneck operations, the plan accounts for operation dependencies, the availability of materials and tools, inspection bookings, and the capacity that equipment can actually provide. It avoids fixing every non-bottleneck job to the minute.

This distinction changes which parameters need close management. In a schedule that specifies every job in detail, the parameters of all operations affect accuracy. The more jobs are scheduled in detail, the more values need to be measured and updated. A bottleneck-centered schedule narrows precise estimation to the bottleneck's processing times and the few other parameters that govern its ability to run.

If delays at an operation repeatedly consume a substantial share of a buffer, recheck its planning values or capacity. Buffer management records progress and arrival at the bottleneck to show how much of the buffer was consumed and which operation caused it. An operation that repeatedly consumes the buffer becomes a candidate for the next round of measurement.

The theory behind this scheduling method is a focus of the EXA Manufacturing Operations Series and will be developed in separate articles.

4. Measuring Bottleneck Machining Time

The first parameter a bottleneck-centered schedule must be able to rely on is the bottleneck's machining time per unit. If that value is too short, the calculation shows the entire bottleneck schedule finishing earlier than it actually will. In the story, Martin used just such an understated standard time when he confirmed Meriden's due date.

The difference can amount to far more than a few minutes per part. If the standard is four minutes too short, the schedule for 120 parts leaves out 480 minutes, or eight hours. The error recurs in the same direction for every unit.

By comparison, in the total machining time of 120 parts run consecutively on one machine, independent variations of a few minutes above or below the mean largely offset one another. One part taking two extra minutes and another taking two fewer minutes cancel out in the total. If every part takes four extra minutes, the full difference accumulates.

This is a total within one machine, distinct from propagation between operations in Section 2. Updating bottleneck parameters primarily corrects this systematic difference, the error in the mean.

In the story, the plant downloaded controller logs to identify the intervals of actual cutting. Many plants cannot access equipment logs. Operators or other responsible staff can collect the same information by timing and recording defined intervals directly. This calls for a dedicated measurement effort with a defined scope and period, without requiring detailed entries for every job. Either method begins by defining what counts as an observation under the same conditions.

Measurements require the following.

  • Define the interval. Set the start and end of machining time per part. For example, if the interval starts when a piece is loaded and ends when machining is complete and the piece is exchanged for the next one, apply that definition to every observation.
  • Separate non-machining time. Record setup, tool changes, waiting for first-piece measurement, and waiting for materials separately from machining time per part. Mixing in waiting understates machining capacity. Include any extra time actually taken because of the operating pace, since it reflects current capacity. Keep setup, tool changes, and waiting in the schedule as separate items according to the resources occupied and the causes.
  • Record the conditions. Record the item, equipment, machining program, material lot, and number of parts measured. Combining observations from different conditions obscures which processing time belongs to which conditions.
  • Repeat the observations. A single smooth run cannot represent normal production. Measure across shifts, days, and material lots to capture the variation that actually occurs.

This last requirement is a separate matter from measurement precision. Even measurements precise to the second will misrepresent ordinary production if they cover only a handful of parts machined by a skilled operator under ideal conditions. Conditions that vary by material lot, such as the tool wear in Chapter 9, show up only when measurements span multiple lots.

5. Updating Estimates from Records

As measurements accumulate, a question arises. When the existing planning value and new records disagree, how many observations justify a change? Revising the standard time on the strength of two observations makes the schedule sensitive to chance deviations. Waiting for dozens of observations keeps a known discrepancy out of the schedule in the meantime.

Bayesian inference gives a single procedure for handling this problem. It starts with the existing planning value and its uncertainty. Each new observation shifts the estimate in proportion to the information it provides. The weights assigned to the existing value and the observations depend on their respective uncertainties. As observations under the same conditions accumulate, their weight increases.

This worked example lets readers follow the calculations by hand to see how updating works. It uses a special case in which the posterior distribution can be calculated directly from a formula, the normal–normal conjugate model.

The model assumes the observation variance is known. On the shop floor, the variance of processing times is not known in advance and must be estimated from records along with the mean. The known-variance assumption is made only in this example so readers can follow the calculation by hand.

The prior for the mean and the observation model both use normal distributions to update the estimate of the mean. The posterior is available directly from a formula, so the example needs no MCMC calculation. Actual processing times often have a long right tail, and both the mean and the spread vary with conditions.

The example illustrates how Bayesian updating works. In practice, the model is chosen after reviewing the measurements and operating conditions.

ItemConditions in the example
TargetMachining time per unit for one item at the bottleneck, including part exchange and excluding setup, tool changes, and waiting
Existing planning valueStandard time of 38 minutes in the master data
Uncertainty in the planning valueThe actual mean may differ from 38 minutes by around 3 minutes (standard deviation of 3 minutes)
Part-to-part variationEven under the same conditions, individual times vary around the mean by about 1.5 minutes (standard deviation of 1.5 minutes)
ObservationsTen measurements for the same item, equipment, and machining program across three shifts and several days: 41, 43, 42, 44, 40, 42, 43, 41, 45, and 42 minutes. The mean is assumed not to vary by shift or day
Model assumptionsA normal distribution centered at 38 minutes (standard deviation of 3 minutes) represents the actual mean. Each observation follows a normal distribution around that mean, with the known part-to-part standard deviation of 1.5 minutes. The observations are independent conditional on the actual mean

The two standard deviations measure different things. Three minutes represents uncertainty about how far the master data value of 38 minutes may be from the actual mean. The 1.5 minutes measures how much individual times vary around that mean even if the mean is known exactly. The mean of the ten observations is 42.3 minutes.

The estimate of the mean is updated as follows.

Updated mean=132×38+n1.52×xˉ132+n1.52\text{Updated mean} = \frac{\dfrac{1}{3^2} \times 38 + \dfrac{n}{1.5^2} \times \bar{x}}{\dfrac{1}{3^2} + \dfrac{n}{1.5^2}}

The terms in the formula are as follows.

  • nn is the number of parts observed and xˉ\bar{x} is the mean of the observations.
  • 132\dfrac{1}{3^2} is the information carried by the existing planning value. Greater uncertainty means less information.
  • n1.52\dfrac{n}{1.5^2} is the information carried by the observations. It increases with the number of observations and decreases with part-to-part variation.
  • The updated mean is a weighted average of the existing planning value and the observed mean, using the information each provides as its weight.

The uncertainty of the estimate depends on the sum of the two amounts of information.

SD of the estimate=1132+n1.52\text{SD of the estimate} = \frac{1}{\sqrt{\dfrac{1}{3^2} + \dfrac{n}{1.5^2}}}

As more information is added, the denominator grows. The standard deviation of the estimated mean therefore decreases as observations accumulate.

With two observations (41 and 43 minutes), the observed mean is 42 minutes. The existing planning value contributes 1/9≈0.111/9 \approx 0.11 and the observations contribute 2/2.25≈0.892/2.25 \approx 0.89, so the observations receive 89% of the weight. Even two observations carry substantial weight because the existing value's uncertainty of 3 minutes exceeds the uncertainty in their mean (1.5/2≈1.061.5/\sqrt{2} \approx 1.06 minutes). The updated mean is about 41.6 minutes and the standard deviation of the estimate is 1.0 minute.

With ten observations, their information increases to 10/2.25≈4.4410/2.25 \approx 4.44 and their weight rises to about 98%. The updated mean is about 42.2 minutes and the standard deviation of the estimate falls to about 0.47 minutes.

ObservationsObserved mean (min)Weight of observationsUpdated mean (min)Standard deviation of the estimate (min)
0—0%38.03.0
242.089%41.61.0
1042.398%42.20.47

Prior and posterior distributions for mean machining time μ, with individual observations shown separately

A schedule for 120 parts shows the scale of the difference. At 38 minutes per part it takes 4,560 minutes, or 76 hours. At 42.2 minutes it takes 5,064 minutes, or 84.4 hours. An error in a single planning value for the mean accumulates to more than eight hours.

The result is an estimate of the mean together with its uncertainty. The planning value applied to the schedule comes from this estimate. The estimated mean becomes the planning value, and uncertainty puts a number on how far actual processing times may depart from it. When the measurement period is short or changes in material lots or machining programs leave few records under the same conditions, uncertainty remains high and the estimate shows its size.

Updating therefore proceeds in the following order. Measurements are used to update the estimate. The result is presented as a proposed change to the planning value. The responsible person reviews the evidence and decides whether to apply it. Approved values enter subsequent plans, and the responsible person determines how to adjust schedules already in progress. If a proposal is declined, the existing planning value stays in place and records continue to accumulate.

EXA solutions use Bayesian inference to learn parameters from actual measurement records collected on that company's own shop floor. With actual processing times, the posterior distribution cannot be calculated directly from a formula as in the worked example, so parameter learning uses Markov chain Monte Carlo (MCMC). MCMC is a stochastic simulation that generates possible parameter values over hundreds of thousands to millions of iterations, based on the actual records and the model.

These samples yield parameter estimates and ranges of uncertainty. As actual shop floor records accumulate, the range of uncertainty narrows and, through the mathematical properties of Bayesian inference, the estimate converges on the true value for that company's operations. The learned result is presented as a proposed change to the planning value, and the user decides whether to apply it. EXA Omni+ follows the same principle for its planning and production parameters.

Even when the estimate converges on the actual value, the schedule still uses a single planning value. The plan is calculated from that one value. Actual times for individual jobs vary above and below it. A more accurate planning value puts the center of that variation in the right place, while the spread remains as variation from job to job.

As Section 2 showed, delays propagate downstream and early finishes do not. Even with an accurate estimate, using one value to fix the time of every job has the same limits as the APS calculation examined earlier.

Buffers absorb the remaining uncertainty. It includes job-to-job variation and the disruptions described by Murphy's Law. Records can keep accumulating, but they cannot tell us in advance when equipment will stop, defects will occur, material will be delayed, or an urgent job will enter the metrology room. As Section 3 showed, buffers before the bottleneck and before shipment absorb delays from individual jobs and disruptions, protecting bottleneck operations and shipment commitments.

Bayesian mathematics brings the parameters the schedule depends on closer to the truth, and buffers absorb variation and disruptions that take operations beyond those values. As the parameters approach actual conditions, less of the buffer is consumed by parameter errors. The remaining consumption reveals variation in the work itself and the effects of disruptions more clearly. Buffer management records then show what to measure next, and those measurements feed the next estimate. When estimation and buffers work together in this way, the schedule keeps uncertainty within the calculation.

6. Accumulating Records and Deciding Whether to Expand Capacity

In Chapter 11, the $1 million equipment expansion request remained in the plant manager's drawer without going to investment review. Whether another machine was needed was a decision for a few months later, when more records would be available. In Chapter 10, the plant manager had also asked Martin to verify actual production capacity and next year's volume.

The previous section's estimate feeds directly into that decision. Calculate the time needed at the bottleneck by multiplying the expected volume by estimated machining time per part and adding setup and tool change times. Start with the equipment calendar to calculate the hours the bottleneck can actually provide, taking into account how much of the downtime for first-piece measurement or material waiting the plant can eliminate. Compare the two figures to determine whether capacity is insufficient.

Five weeks of records were still insufficient. Setup time had fallen from 90 to 25 minutes, but the five-axis downtime logs still showed long waits for first-piece inspection, tools, and materials. Capacity measured while operational improvements are in progress differs from capacity once they are complete.

The decision must also account for future load. Meriden said it would place a follow-up order for 300 sets after reviewing the schedule and the evidence for capacity. Five weeks later, Machine 1 was machining the first batch from that order. The capacity decision includes confirmed orders and expected volumes.

As the records accumulate, uncertainty about machining time per part at the bottleneck decreases, and the distinction between downtime that operations can reduce and downtime they cannot becomes clearer. From the perspective of this commentary, by holding the request rather than cancelling it, the plant manager deferred the decision until both points could be established.

The following questions provide a starting point for examining the same problem at another plant.

  1. When and under what conditions was the standard time used in scheduling set? Was it updated after changes to the geometry, material, or machining program?
  2. Do operating records separate setup, tool changes, waiting for measurement, and waiting for materials from machining time?
  3. Which operation's planning parameters determine schedule accuracy? Have those values been checked through repeated observations under the same conditions?
  4. Are there buffers and spare capacity to absorb errors at non-bottleneck operations? Which operations repeatedly consume the buffers?
  5. When new records differ from existing planning values, who reviews the difference and when does it enter the schedule?

The plant in the story reconciled its records, confirmed that its planning values differed from actual conditions, and logged what stopped the five-axis machines for five weeks. Meriden also asked for the evidence behind the schedule and the capacity estimate before placing its follow-up order. The next episode takes up the evidence a plant uses to quote a due date before accepting a new order.


Next · MFG EP02

What evidence does a plant use to promise a due date before accepting a new order? The next episode examines how it checks standard lead times, current loads, bottleneck capacity, and orders already promised before quoting a due date.